A factory acceptance test (FAT) is the formal inspection and functional test of a control panel at the manufacturer’s factory, carried out before the equipment ships. It proves that the panel is built to the approved drawings, that the hardware and software work together, and that it meets the agreed specification, while problems are still cheap and quick to fix.
This guide explains the FAT procedure step by step, gives you a practical FAT checklist for control panels, and covers what is different about a PLC panel FAT. Whether you are a buyer, project engineer, or site manager, you can use it to plan, witness, and sign off a FAT with confidence.
What Is a Factory Acceptance Test?
A factory acceptance test is a documented series of checks performed on a finished control panel, in the supplier’s workshop, with the customer or the customer’s representative invited to witness. The panel is powered up, inputs and outputs are simulated, and every function is tested against the approved specification.
A FAT is different from the routine tests that every cabinet receives during production. Routine tests confirm that the assembly is safe and correctly built. The FAT goes further and demonstrates that the whole system, including hardware, wiring, software, and interlocks, behaves the way the customer expects.
It is also not the same as a site acceptance test (SAT). The FAT happens before shipment, in a controlled environment. The SAT happens after installation, with real field devices, motors, and process conditions, and is often supported by project commissioning engineers.
Why a Factory Acceptance Test Matters
Finding a fault at the factory is far cheaper than finding it on site. A thorough FAT helps you:
- Reduce commissioning time. Wiring errors, wrong I/O addresses, and logic faults are fixed before the panel leaves the workshop.
- Avoid costly site delays. Rework on an operating plant means crane hire, shutdown windows and idle contractors.
- Confirm the specification is met. The test record is objective evidence that the panel matches the purchase order, drawings and standards.
- Create a clear handover. Signed FAT records form part of the documentation package and make future maintenance easier.
- Build trust between buyer and supplier. Both sides agree on what “accepted” means before money and equipment change hands.
Before the FAT: Preparation
A good FAT starts weeks before the test day. Agree the following in advance:
- FAT scope and test plan. Decide which panels, functions, and software are covered, and who writes the test sheets.
- Approved documents. Final electrical schematics, layout drawings, I/O list, cause-and-effect matrix, functional description, and the bill of materials should all be frozen and approved.
- Acceptance criteria. For every test, define what a pass looks like (for example, “valve opens within 5 seconds of the command”).
- Attendees and roles. Name the supplier’s test engineer, the customer’s witness, and any third-party inspector.
- Test equipment. Calibrated multimeters, insulation testers, signal simulators, and a laptop with the correct software version should be ready and listed.
- Schedule and logistics. Confirm the date, working hours, and whether the witness will attend in person or by video.
FAT Procedure: Step-by-Step
The exact order depends on the project, but a typical FAT procedure for a control panel follows these stages.
Step 1: Documentation and Design Review
Compare the as-built panel against the approved drawings, bill of materials, and specifications. Check that the document revision numbers match the revision on the panel’s drawing pocket. Any deviation must be recorded and approved before testing continues.
Step 2: Visual and Mechanical Inspection
Walk through the enclosure with the drawings in hand and check:
- Enclosure type, material, paint finish, and IP rating
- Door fit, hinges, locks, gaskets and mounting plate
- Component brands, model numbers and ratings against the bill of materials
- Cable routing, trunking and bend radius
- Labels, nameplates, wire numbers and terminal markings
- Ventilation, fans, filters or air-conditioning where specified
- Cleanliness, with no metal swarf, loose screws, or damaged components
Step 3: Wiring and Termination Check
Confirm that each wire is correctly landed, tight, and tagged. Point-to-point continuity testing (often called “ringing out”) verifies the power, control and signal wiring against the schematics. Spot checks on terminal torque are common practice.
Step 4: Electrical Safety Tests
Before the panel is energised, run the standard safety tests required by the project and the applicable standard, for example:
- Insulation resistance test
- Protective earth continuity test
- Dielectric (high-voltage withstand) test, where specified
- Verification of protective measures and clearances
Low-voltage assemblies are usually built and verified to IEC 61439, and medium-voltage switchgear to the IEC 62271 series, with any additional client or local requirements applied as specified.
Step 5: Power-Up and Power Supply Verification
Energise the panel in stages. Check incoming voltage, supply polarity, 24 V DC power supply output, fuse and breaker ratings, and the operation of surge protection and UPS units where fitted. Confirm that no component overheats or trips during initial energisation.
Step 6: Functional and Software Testing
This is the core of the test. The test engineer simulates field signals and checks the panel’s response against the functional description:
- Digital and analogue I/O checks: every input and output is tested individually against the I/O list, including scaling and ranges.
- Control logic and sequences: start-up, shut-down, auto and manual modes, set points and timers.
- Interlocks and permissives: each interlock is forced and confirmed.
- Alarms and trips: alarm messages, priorities, acknowledge and reset behaviour.
- Emergency stop and safety circuits: verified for correct action and reset.
- HMI and SCADA: screens, navigation, data display, trends and operator commands.
- Communications: Modbus, PROFIBUS, PROFINET, Ethernet/IP or other protocols tested with the master and slave devices.
- Failure behaviour: loss of power, loss of communication, and sensor failure should leave the system in the specified safe state.
Step 7: Punch List and Corrective Actions
Every failed test or observation goes on a punch list with a unique number, a description, a responsible person, and a due date. Minor items may be closed during the FAT. Critical items require a re-test of the affected function.
Step 8: Final Review and Sign-Off
Once the punch list is cleared or formally accepted with agreed actions, both parties sign the FAT report. The signed record states whether the panel is released for shipment, released with conditions, or rejected pending re-test.
Step 9: Packing and Shipment Readiness
Before leaving the factory, confirm that the panel is protected for transport: shock and moisture protection, secured doors and loose items, correct marking, and the full documentation set (drawings, manuals, test reports, and the signed FAT report) packed with the equipment.
PLC Panel FAT: Extra Points to Check
A PLC panel FAT adds software and communication checks on top of the hardware inspection. Pay special attention to:
- Software version control. Record the PLC, HMI, and SCADA program versions tested, with checksums or file names, so the version installed on site is the version that was accepted.
- I/O simulation. Use simulator boxes, forcing, or a software test harness so that every input and output can be exercised without the real process.
- Redundancy tests. If the panel has redundant CPUs, power supplies or networks, switch over and confirm bump-free operation.
- Cybersecurity basics. Check password protection, user levels, and disabled unused ports.
- Backup and restore. Prove that the program can be saved and reloaded onto a replacement CPU.
- Documentation. Provide the final source code, tag lists, network diagram, and I/O list as agreed in the contract.
For a deeper look at what goes inside these panels, see our guide to PLC / DCS cabinets and software.
Related guides: How to choose a PLC panel supplier, PLC vs DCS: which control system is right for your plant?, What is a VFD cabinet? High voltage vs low voltage switchgear and our waterworks automation project case.
Common FAT Mistakes to Avoid
- Starting with unapproved drawings. Testing against a moving target causes disputes.
- Vague acceptance criteria. “Works correctly” is not a criterion; measurable limits are.
- Skipping failure scenarios. Panels should be tested for what happens when things go wrong, not only when everything works.
- No software version record. Without it, site and factory programs can quietly diverge.
- Rushing the schedule. A FAT squeezed into a few hours usually becomes a long SAT.
- Unclear punch list ownership. Every open item needs an owner and a date.
FAT, SAT and Routine Tests Compared
| Test | Where | When | Main purpose |
|---|---|---|---|
| Routine test | Factory | During and after assembly | Confirm safe, correct build of each unit |
| Factory acceptance test (FAT) | Factory | Before shipment | Prove the full system meets the specification |
| Site acceptance test (SAT) | Customer site | After installation | Prove the system works with real field equipment |
How Danli Handles the Factory Acceptance Test
At Danli, every cabinet is routine-tested, and control systems go through a factory acceptance test that you can witness in person or by video. Our engineers prepare the test plan from your approved drawings and I/O list, because design, production, software, and testing are handled by one team. Interfaces between switchgear, drives, and PLC systems are coordinated from the start, and you receive one consistent documentation set. We also supply export projects with English documentation, suitable packaging, and commissioning support on site or remotely.
Frequently Asked Questions
What is a factory acceptance test in simple terms?
A factory acceptance test is a formal check of a finished control panel at the manufacturer’s factory, done before shipment. It confirms the panel is built to the drawings and works as specified.
Who should attend a FAT?
The supplier’s test engineer and the customer’s representative are the core attendees. Many projects also include a third-party inspector, the end user’s operations staff, and the commissioning engineer.
How long does a FAT take?
A small PLC panel may take a few hours. A large multi-panel control system with SCADA and many I/O points can take several days. Plan the time based on the number of I/O points, functions, and interlocks.
Can a FAT be witnessed remotely?
Yes. Many suppliers offer live video witnessing, which is useful for international projects. Agree in advance on camera positions, screen sharing, and how test records will be shared.