A high and low voltage switchgear manufacturer builds the panels that receive power at medium or high voltage and the assemblies that share it out at low voltage to motors, lighting and process loads. Choosing one switchgear supplier for both sides means one team is responsible for how the two systems connect, protect each other and communicate.
This guide is about the buying decision, not the theory. If you need the technical differences between the two voltage classes first, read our six key differences between high and low voltage switchgear. Here we cover what a manufacturer supplies, when a single supplier makes sense, where the two sides meet, which ratings to specify and which mistakes to avoid. It draws on the experience of the Danli engineering team in Binjiang District, Hangzhou, who build both voltage classes.
Key takeaways
- A single supplier is not always cheaper, but it removes the gap between two contracts at the point where faults are most likely to be blamed on someone else.
- The low voltage assembly must be rated above the fault current the transformer can deliver. Check this before you compare prices.
- Medium voltage relay settings and low voltage breaker settings must be coordinated so a small fault does not shut the whole plant.
- Ask for type test reports for the exact panel design, and a routine test report for each panel you receive.
What does a high and low voltage switchgear manufacturer supply?
A full-range supplier covers the incoming medium or high voltage panels, the low voltage distribution and motor control sections, and the engineering that joins them.
| Scope | Typical items | Danli reference |
| High voltage side | Metal-clad withdrawable panels with vacuum circuit breakers, busbars, protection relays, instrument transformers | KYN28-12 metal-clad switchgear and high-voltage switchgear |
| Low voltage side | Distribution boards, motor control centres, incomers and feeders | Low-voltage switchgear |
| Engineering and services | Single-line diagram review, factory acceptance testing, commissioning support | Project commissioning |
Should you buy HV and LV switchgear from one supplier?
Often yes, but not always. This table shows the trade-offs.
| Factor | One supplier | Two suppliers |
| Responsibility at the interface | One party owns the connection | You manage the gap between contracts |
| Protection coordination | Settings checked as one system | You must coordinate two sets of data |
| Testing | One factory acceptance test | Two tests, two schedules |
| Price comparison | Harder to compare line by line | Easier to bid each side separately |
| Specialist depth | Depends on the supplier’s strength in both | Pick the best specialist for each side |
Choose one supplier for both sides when the plant has a single substation feeding a process, when the schedule is tight, or when your own team has limited switchgear engineering time.
Choose two suppliers when one side is a very large or unusual specification, such as a very high current main board, and a specialist is clearly better for it.
Where do high and low voltage switchgear meet?
The risks sit at six connection points. Ask every switchgear supplier on your shortlist how they handle each one.
| Interface | What to check | What goes wrong if ignored |
| Short-circuit level | The low voltage assembly must be rated above the fault current at its busbars | An undersized assembly that cannot survive a fault |
| Protection coordination | Medium voltage relay settings and low voltage breaker trips must be selective | A small low voltage fault trips the medium voltage incomer |
| Transformer connection | Cable or busduct entry, termination space, current transformer location | No room to terminate cables |
| Control power | Auxiliary supply voltage and backup for relays and breaker coils | Mismatched control voltages between panels |
| Communications | Relay and meter protocols, such as Modbus or IEC 61850 where used | Extra gateways and delayed commissioning |
| Earthing and interlocks | Earthing arrangement and key interlocks between the two sides | A safety gap during maintenance |
Worked example. A 1,000 kVA transformer at 400 V with 6% impedance can supply roughly 24 kA at its low voltage terminals. The calculation is rating divided by (1.732 × voltage × impedance), before cable impedance and without the supply network. The low voltage busbars and breakers must be rated above that figure. Your supplier should confirm the number with the real transformer data.
Which ratings should you specify?
| Rating | What it tells you | Common mistake |
| Rated voltage | The highest voltage the equipment is built for | Specifying 10 kV equipment for a 10 kV system, when the standard equipment class is 12 kV |
| Rated current | Continuous current for busbars and feeders | Ignoring load growth and hot sites |
| Short-time withstand current | The fault current the busbars survive for a set time, often 1 or 3 seconds | Checking the breaker only and forgetting busbars and current transformers |
| Breaking capacity | The fault current the breaker can interrupt | Assuming it equals the withstand rating |
| IP rating | Protection against dust and water | Specifying indoor equipment for a dusty plant room |
| Internal arc classification | Operator protection if an internal arc occurs | Assuming every panel has it, when it is optional |
| Site conditions | Altitude and ambient temperature limits | Ordering standard equipment for a hot or high-altitude site |
HV/LV Coordination Checklist
Whether you use one supplier or two, these interface points must be agreed in writing before manufacturing starts. Most site delays come from one of them:
- Transformer data – kVA rating, impedance and vector group must match both the MV protection settings and the LV incomer breaker rating.
- Fault levels – the LV board must withstand the prospective short-circuit current that the transformer can deliver, not just the normal load current.
- Protection coordination – MV relay curves and LV breaker trip settings should be graded so the breaker closest to a fault trips first.
- Busbar and cable entries – check top or bottom entry, cable sizes, number of cores and gland plates on both line-ups.
- Interlocks and transfer schemes – key interlocks, bus couplers and generator changeover logic often span both HV and LV equipment.
- Control power and communication – agree the auxiliary voltage, battery/UPS supply and the protocol used to send breaker status and metering to SCADA.
Recording these points in a single interface document, signed off by both sides, is the simplest way to avoid rework during commissioning.
Which documents should you ask for before you order?
Request these in writing from each supplier and compare them side by side:
- A single-line diagram showing every rating.
- Short-circuit and protection coordination data.
- Type test reports for the exact panel design.
- A bill of materials naming breaker, relay and meter brands.
- General arrangement drawings with cable entry positions.
- A factory acceptance test procedure.
- A spare parts list and operation manuals.
If you need help reading the single-line diagram, see our beginner’s guide to switchgear single-line diagrams.
Five mistakes buyers make with switchgear
- Comparing prices without matching brands: A cheaper quote may use a lower-tier breaker or relay.
- Skipping spare bays: Plan at least one spare feeder per section so the plant can grow.
- Forgetting cable entry: Top or bottom entry changes the room layout and civil work.
- Ignoring site conditions: Heat, dust, humidity and altitude change the design.
- Not asking which tests apply: A test on a similar panel is not a test on yours.
Why work with Danli?
Danli manufactures KYN28-12 metal-clad switchgear for medium voltage distribution and low voltage distribution boards and motor control centres. Our KYN28-12 panels use VS1-12 and VH1-12 vacuum circuit breakers as standard, with other recognised breaker types possible by project. Our engineers support projects from specification through factory acceptance testing to commissioning, and our systems serve water treatment, metallurgy, oil and gas and distribution networks.
Danli publishes its certificates and test reports on the qualifications page. Compare the scope and date of each one with the product you plan to buy.
Related reading: KYN28-12 switchgear full guide, project cases for low-voltage switchgear and high-voltage cabinet projects. For the automation side of the same plant, see our guide to choosing a PLC control cabinet manufacturer.
Frequently Asked Questions
It is better when the two sides must work as one system and the schedule is tight. One supplier is responsible for coordination, testing and delivery. Use two specialists only when one side has an unusual specification.
Type tests prove that the panel design meets the standard, and they are done once on a representative design. Routine tests check every panel that is built, including wiring, mechanical operation, interlocks and insulation. Ask for both.
Delivery depends on long-lead items such as vacuum circuit breakers and protection relays, drawing approval, and testing. Complete drawings and a confirmed bill of materials at the start shorten the schedule.
Yes, but tell the supplier early. Standard designs are generally rated for sites up to 1,000 m and 40 °C maximum ambient, so higher or hotter sites need derating or a special design.
Under IEC practice, equipment above 1,000 V AC is high voltage and equipment at or below that is low voltage. The details are in our high vs low voltage switchgear guide.
There is no fixed price. Cost depends on voltage class, current and short-circuit ratings, breaker and relay brands, number of panels, protection, metering and testing scope. Send your single-line diagram for an accurate quote.